1, the machine installation should consider supporting the project power, water, space, material transport channel and rainproof measures.
2, the installation site need to smooth, solid foundation, foundation pit is slightly higher than the ground, to water into the pit.
3, according to the foundation pit excavation, according to the local geological conditions, foundation pit size can be increased to deepen.
4, on the cross on the top of the foundation pit two channel steel, used heavy equipment will be main frame and a movable door frame lift on the channel above, the anchor bolt wear to the machine base, and screw on the nut but do not tighten, to pour good foundation then tighten the.
5, then put suspended roller shaft hoist with bolt fixed on the main frame of the coupling, this suspension roll axis of wire rope shall not be relaxed, the suspended roller shaft is inserted into the door frame of the taper hole, finally with the level of instrument to suspended roller leveling alignment.
6, the mixing of concrete perfusion to the inside of the foundation pit, the concrete strength grade shall not be less than C20, and the vibrator compacting, should not have pores.